Posted on: February 28, 2020

Annual Maintenance of the Sanitary Sewer Collection System

UpcomingProjectWork

Water Pollution Control - Upcoming Project

Annual Maintenance of the Sanitary Sewer Collection System

As part of the annual maintenance on the collection system, staff has identified 10 sewer mains totaling 2,380’ and 50 laterals that need to be repaired by lining them. Along with the sewer mains, city will also be repairing 10 manholes. 

Both projects will help with the reduction of Inflow & Infiltration (I&I) in the collection system. Below is the tentative schedule given to the city by the contractors. All work is weather dependent so the schedule may change slightly.

Sewer Main Lining:

SAK Construction from O’Fallon Missouri
Sewer Main Line Map

  • SAK’s subcontractor Accujet from Perry will be here the week of March 2, 2020 to perform cleaning and televising of the sewer mains
  • March 16, 2020 – SAK will be in town to start lining the sewer mains. Contractor anticipates it taking about one week.
  • March 30, 2020 – SAK will be back in town to perform the lateral lining

Manhole Repair:

Hydro-Klean from Des Moines
Manhole Repair Map

  • March 2, 2020 - Will start working on the manhole repairs with an anticipation of 2 weeks to perform the work.

Maps showing the locations of the work to be performed are on the Water Pollution Control Department page under Upcoming Projects.


Water Pollution Control Upcoming Projects